On August 7, OpenAI said it was pausing pieces of its next model, Astra, until they cleared strengthened security controls (OpenAI, 2026a). Three weeks later, on September 1, it said so more plainly: parts of Astra’s development and release had been delayed for several weeks while the company strengthened and tested new safeguards (OpenAI, 2026b). In early September, GPT-6 Astra shipped. It sits on OpenAI’s developer page right now (OpenAI, 2026c).
This isn’t a story about a company that didn’t know what it was doing. Astra came from one of the best-resourced model-building teams on the planet, working with more visibility into its own project than any outside forecaster could ever have. The plan still needed revising twice before it shipped. That’s not incompetence. It’s a pattern behavioral scientists have documented for nearly fifty years.
Why the inside view always wins
Daniel Kahneman and Amos Tversky named it the planning fallacy: the tendency to forecast a project from the story of how it’s supposed to go, rather than from what happened to comparable projects before it (Kahneman & Tversky, 1979). Kahneman and Lovallo (1993) explained why the error survives experience — forecasts anchor to the plan itself, not to history, so every new project gets treated as the exception.
Buehler, Griffin, and Ross (1994) measured the gap directly. They asked students to predict how long their senior thesis would take. Best-guess estimate: 33.9 days. Explicitly pessimistic estimate, built to account for everything that could go wrong: 48.6 days. Actual average completion time: 55.5 days. Only 29.7% finished within their own best-case estimate.
The uncomfortable finding isn’t that the optimistic estimate missed. It’s that even the pessimistic one did.
It isn’t a scheduling problem — it’s a forecasting problem
Swap “thesis” for “deal,” “launch,” or “quarter,” and the mechanism holds exactly. Sit in a pipeline review and listen to how a forecast gets built: procurement is engaged, the champion confirmed budget, legal is “almost done.” That’s the inside view — a detailed story about this specific deal. What rarely enters the room is the outside view: how long deals this size, in this vertical, with this many stakeholders, have actually taken to close historically.
The cost compounds at scale. Flyvbjerg, Holm, and Buhl (2003) studied 258 transport infrastructure projects across 20 countries and found average cost overruns of 45% for rail, 34% for bridges and tunnels, and 20% for roads. In technology delivery the risk skews worse — Flyvbjerg, Budzier, Lee, Keil, Lunn, and Bester (2022) analyzed 5,392 IT projects and found cost overruns follow a power-law distribution: mostly small misses, with a fat tail of catastrophic ones. A revenue forecast built as a single-point estimate is blind to exactly that tail.
The same blind spot sets next year’s number before a single rep carries a quota. Annual plans get built from a bottoms-up story — new logos per rep, ramp time, win rate — rather than from what the company’s own pipeline has actually converted at, quarter over quarter, for years. And a launch date matters beyond the launch itself: every week a product slips past its planned ship date is a week sales enablement, pricing, and campaign timing were built around a date that was never going to hold, which is its own drag on the quarter.
One honest caveat belongs here. Not every optimistic number is the planning fallacy. Kahneman and Lovallo (1993) distinguished it from strategic misrepresentation — a forecast that’s deliberately aggressive because that’s the number required to win budget or board approval. The fix for the first is better information. The fix for the second is different incentives. Leaders who conflate the two end up “de-biasing” a number that was never meant to be accurate in the first place.
What the fix actually looks like
Sydney’s Opera House is the classic illustration of the failure mode — forecast in 1957 to open in 1963 for about A$7 million; it opened a decade late, in 1973, for a reported A$102 million (Buehler et al., 1994; NSW Government, n.d.). Less discussed is what fixed it going forward. The UK began mandating reference class forecasting — grounding every new budget in the empirical outcomes of comparable completed projects — for major public projects in 2003. Park (2021) studied 107 of those projects before and after adoption: average cost overrun fell from 38% to 5%. Not a rounding error. A structural correction, because it replaced “how we think this will go” with “how things like this actually go.”
A base-rate test for revenue leaders
Three questions substitute for the instinct to trust the story:
- What did deals, launches, or projects like this one actually take, historically — not what the plan says this one should take? That’s the reference class. If nobody in the room can answer it, the forecast is a guess wearing a date.
- What’s the evidence behind this date, versus the narrative? A verbal commitment and a signed contract are not the same fact. Treating them as interchangeable is how a forecast quietly turns into fiction.
- Who is reviewing this number who didn’t build it? The person who wrote the forecast has the least incentive to challenge it. An independent read — a RevOps forecast call, a second set of eyes with no stake in being right — is the cheapest correction available.
OpenAI didn’t need this framework to ship a working model; it had the safety data to justify the delay twice over. Most companies don’t have that kind of margin for error. The date quietly running your quarter is rarely on anyone’s dashboard. It’s usually the number the story says should be true, not the one the history says probably will be.
References
Buehler, R., Griffin, D., & Ross, M. (1994). Exploring the “planning fallacy”: Why people underestimate their task completion times. Journal of Personality and Social Psychology, 67(3), 366–381. https://doi.org/10.1037/0022-3514.67.3.366
Flyvbjerg, B., Budzier, A., Lee, J. S., Keil, M., Lunn, D., & Bester, D. W. (2022). The empirical reality of IT project cost overruns: Discovering a power-law distribution. Journal of Management Information Systems, 39(3), 607–639. https://doi.org/10.1080/07421222.2022.2096544
Flyvbjerg, B., Holm, M. K. S., & Buhl, S. L. (2003). How common and how large are cost overruns in transport infrastructure projects? Transport Reviews, 23(1), 71–88. https://doi.org/10.1080/01441640309904
Kahneman, D., & Lovallo, D. (1993). Timid choices and bold forecasts: A cognitive perspective on risk taking. Management Science, 39(1), 17–31. https://doi.org/10.1287/mnsc.39.1.17
Kahneman, D., & Tversky, A. (1979). Intuitive prediction: Biases and corrective procedures. TIMS Studies in Management Science, 12, 313–327.
NSW Government. (n.d.). The house the lotteries built. https://www.nsw.gov.au
OpenAI. (2026a, August 7). Pacing model development in an era of cyber-critical capabilities. https://openai.com/index/pacing-model-development-cyber-capabilities/
OpenAI. (2026b, September 1). Path to Astra: Critical capabilities and frontier safeguards. https://openai.com/index/path-to-astra/
OpenAI. (2026c, September). GPT-6 Astra: The next generation in intelligence for work [Product page]. https://openai.com/
Park, J. E. (2021). Curbing cost overruns in infrastructure investment: Has reference class forecasting delivered its promised success? European Journal of Transport and Infrastructure Research, 21(2), 120–136. https://doi.org/10.18757/ejtir.2021.21.2.5504